An ERP implementation runs in five phases: requirement confirmation, configuration, data migration, training with a parallel run, then go-live and stabilisation. A single-unit factory with clean master data takes about 90 days. Most slippage happens in migration, and most of that is caused by data nobody had cleaned.
Five, and they overlap rather than finishing cleanly one after another. The timeline below assumes a single unit, one process type, a named champion with decision authority, and master data that exists in one place. Remove any of those four and add a month.
The column worth arguing about before signing is the last one. An implementation where your own people have no allocated hours is an implementation that will slip, because every phase after configuration depends on work only your staff can do.
| Phase | Weeks | Vendor does | You do |
|---|---|---|---|
| Requirement confirmation | 1 to 2 | Walks your process, writes the configuration spec | Confirm it matches reality, not the org chart |
| Configuration | 3 to 6 | Builds chart of accounts, item structure, workflows, approvals | Answer questions within a day, not a week |
| Data migration | 4 to 8 | Extract, load, reconcile opening balances | Clean the item master, suppliers and customers |
| Training and parallel run | 7 to 11 | Train by role, support both systems | Run old and new together, reconcile daily |
| Go-live and stabilisation | 12 to 13 | On-site support, fix what surfaces | Stop using the old system on the agreed date |
Your process gets written down, probably for the first time. The vendor walks each department, records how work actually flows, and produces a configuration specification. Your job is to confirm it describes reality rather than the procedure manual nobody follows.
This is the phase where factories discover their own undocumented practices. Two departments numbering orders differently. A costing sheet with a hard-coded wastage percentage somebody set years ago. A store issuing material against a verbal instruction. None of these is unusual and all of them have to be decided before configuration, because the system will enforce whichever version you choose.
Expect to settle questions you have been deferring for years. That is the real work of weeks one to four, and it is why the champion needs authority rather than availability.
Data. Specifically, somebody opens the item master and finds the same yarn count under four names, three supplier records for one company, and no agreed convention for new items. Migration was quoted on volume and the actual problem is condition.
This is the most reliable failure point in the whole project and it is almost entirely preventable. The cleaning can start before the vendor arrives: consolidate every item into one file with one naming convention, retire duplicate suppliers, and agree who creates new codes and to what rule. Six weeks of your own staff's attention here removes most of the cost and a chunk of the elapsed time.
The second week-three problem is quieter. The champion discovers the project is a second full-time job and their first one has not gone away. Where nobody notices, the project slows for a month before anyone says so. Allocate the hours formally or expect this.
If you are still in selection, our seven-step ERP selection process puts data cleaning in step one for exactly this reason.
Running the old process and the new system together for a period, entering the same transactions in both and reconciling daily. It is tedious, it roughly doubles data entry for three or four weeks, and skipping it is the most expensive saving available in an ERP project.
The parallel run is where you find out whether the configuration is right while the old system is still there to fall back on. Discrepancies at this stage are cheap: somebody investigates a variance and a workflow gets corrected. The same discrepancy found after cut-off is a production incident.
Two rules make it work. Reconcile daily rather than weekly, because a week of divergence is hard to trace. And agree in advance, in writing, what level of agreement ends the parallel run, so cutting over is a criterion rather than an argument.
Four weeks is typical for a single unit. Composite groups usually run longer and sometimes phase it unit by unit, which is slower in total and lower risk.
Not at go-live. An implementation is finished when no department maintains a parallel spreadsheet it trusts more than the system, which is usually three to six months after cut-off and sometimes never. Go-live is the start of stabilisation, not the end of the project.
The honest test is to walk the floor and the finance department looking for notebooks and workbooks. Anything still running outside the system after six months is a process that was configured wrong, and the reason is usually a screen slower than writing by hand. Find the reason rather than banning the notebook.
The second test is the champion. If the person who understands the system leaves in month four, which happens more often than anyone plans for, does a handover pack exist and is training repeatable? Ask that question at signature, not in month four.
For how the order, cutting, work in progress and bond modules are configured against a single order record, see our garments ERP software page.
What is the ERP implementation process? Five phases: requirement confirmation, configuration, data migration, training with a parallel run, then go-live and stabilisation. They overlap rather than completing one at a time. A single-unit factory with clean master data takes roughly 90 days from kick-off to cut-over.
How long does an ERP implementation take? Three to four months for a single unit with clean data and a champion who can decide. Eight to twelve months for a composite group with spinning, weaving, dyeing and garments. Add about two months if your item master exists in more than one spreadsheet.
What is the most common reason ERP implementations slip? Data migration, and specifically data condition rather than volume. Duplicate item codes, multiple supplier records for one company and no convention for new codes turn a load into a cleaning project. Most of it can be fixed by your own staff before the vendor starts.
What is a parallel run in ERP implementation? Running the old process and the new system together for three or four weeks, entering the same transactions in both and reconciling daily. It is where configuration errors get found while the old system is still available as a fallback. Skipping it is a false saving.
Who should lead an ERP implementation on the factory side? A champion with decision authority rather than spare time, supported by named people in each department with allocated hours. The most expensive projects are those where the assigned person must refer every question to a director's meeting.
What happens at ERP go-live? The agreed cut-off date passes and the old system becomes read-only. The vendor provides on-site support while problems surface and get fixed. Go-live begins stabilisation rather than ending the project, and the first month-end close after it is the real test.
When is an ERP implementation complete? When no department keeps a parallel spreadsheet it trusts more than the system. That is typically three to six months after go-live. Any process still running in Excel at that point was configured wrong, and the reason is worth finding rather than overruling.